C onstruction P rocess

Interior Finish and Pool Filling  Following completion of all agreed-upon items, our Team schedules the pool plaster application. Once applied, the plaster undergoes the necessary curing process, at which point the pool is filled. Start Up/ Pool School  Once the pool is

1) Design

2) Layout

3) Excavation

4) Forming & Rebar

filled and operational, the in-house Service Department conducts the initial start-up. A Pool School session is then scheduled to provide the homeowner with comprehensive instruction, ensuring full confidence in the maintenance and enjoyment of the new pool.

5) Plumbing & Electrical

6) Gunite Application

7) Tile, Coping & Masonry

8) Decking

9) Screen Enclosure

10) Interior Finish

11) Finished Pool